WHAT REMAINS UNRESOLVED
Recorded exceptions from the committed validation and decision logs. Applied model inputs can still have unresolved evidence. Historical register actions are shown separately in the risk explorer.
Supplier quotes; controls-panel quote still open · Committed input: $1.5M most likely, $1.4M / $1.6M range (P10 / P90, framework 9.2)
Priya Nair, Supply Chain Manager · 05_qsra/inputs/validation_log.csvRedefined event; liquid-ready design option cost open · Committed input: $4M / $6M / $10M
Marcus Hale, Engineering Manager · 05_qsra/inputs/validation_log.csvNew Altair-caused threat · Committed input: 30%; NTP (M01) slips 10 SITE5 wd, 2027-01-04 to 2027-01-18 (single point); owner-caused
Raj Patel, Project Manager · 05_qsra/inputs/validation_log.csvReduces late-change impact for both parties
Raj Patel with Kevin Marsh (Altair) · 09_records/decision_log.csvNo reply from Gulf Coast Power; backfeed readiness 2027-09-16 is after the utility's 2027-08-31 date
Raj Patel (Project Manager) · 09_records/decision_log.csv